CORE CAPABILITY

QA & System Testing

Testing every layer before sign-off. DHCP per VLAN, guest isolation, WAN failover, Wi-Fi coverage and roaming, spanning tree, PoE, IGMP and PTP clock lock.

How I approach it

  1. Write the schedule first. The test schedule is written from the design, so every requirement has a test.
  2. Test each layer. DHCP on every VLAN, guest isolation, WAN failover, Wi-Fi coverage and roaming, spanning-tree root, PoE draw, IGMP querier and snooping, and PTP clock lock.
  3. Test for time, not just a moment. Dropout tests over a set period, and recovery after switches are power-cycled.
  4. Record every result. Pass or fail, with notes, in the commissioning record handed to the client.

Why I work this way

QA is my job, and it’s the part I care most about. A schedule turns “it seems fine” into evidence. It catches the faults that only show up under load or after a power cut, and it gives the client and the next engineer a clear record of what was proven.

Tools I use

Written test schedules, Afara, Dante Controller, switch and Wi-Fi management tools.